On Exciting progress is underway as Missouri S&T’s Welcome Center construction continues to progress. The redesign and incorporation of the north plaza are in motion, and mechanical work in the basement is now 95% complete.
The Welcome Center Committee was invited to a construction site walkthrough this week on Wednesday, March 5, which offered an opportunity to see the progress firsthand.
Despite some weather-related delays due to snow, construction remains on track, with brick and masonry work scheduled to begin on Monday, March 10. Curtainwall framing has been delivered, and installation will start immediately on the south facade. Glass has also arrived on-site.